Budget position
BudgetAED 124,000,000
CommittedAED 9,600,000
ActualAED 112,900,000
RemainingAED 1,500,000
Forecast at completionAED 123,940,000
StatusAt risk
Cost breakdown
DirectAED 98,100,000
IndirectAED 8,900,000
OverheadAED 5,900,000
Direct costs
| Category | Document | Amount | Status |
|---|---|---|---|
| Construction | INV-AN-4912 · Al Noor | AED 85,000 | Pending approval |
Indirect costs
| Category | Cost centre | Amount | Status |
|---|---|---|---|